7 October 2026

Reduced Capital Circle speed limit, no more bridge expansion: the new plans for light rail stage 2B revealed

| By Claire Fenwicke
Start the conversation
artist impression of light rail stage 2B

The final environmental impact statement documents see light rail stage 2B going under parts of Commonwealth Ave. Photo: ACT Government.

New track arrangements, more kiss-and-ride stops and reduced speed limits are some of the changes made in the final environmental impact documents for light rail stage 2B.

It only assesses the State Circle East alignment – a route that was confirmed by the ACT Government in May.

One major change is that the Melrose Drive Bridge over Yarralumla Creek will no longer be widened by about 7.5 metres (to accommodate extra southbound traffic) during stage 2B’s construction.

The impact of such construction works was a key concern raised in community submissions, including potential safety risks and the increased use of, or shortcutting by motorists through, nearby roads such as Theodore Street.

“Construction of these works would have likely required all traffic between Melrose Drive and Yarra Glen to be temporarily redirected to Launceston Street, Theodore Street or drivers would have to alter their route entirely,” the documents stated.

Extra traffic modelling was undertaken to see what other options were available outside of widening the bridge. Conservative 2041 traffic forecasts showed road performance (including queuing along Melrose Drive toward the Theodore Street intersection) would be similar when comparing the bridge-widening option with an alternative design that shifted the lane configuration further south.

In light of the findings, the bridge widening is no longer proposed.

“This change will avoid the need to close sections of Melrose Drive and Yarra Glen completely during construction while achieving similar traffic outcomes when the project is operational.”

READ ALSO State Circle it is for light rail to Woden, but there are changes

An additional aspect is the proposed reduced speed limit for parts of Capital Circle.

After the draft EIS exhibition period, further design reviews identified a traffic safety risk at the crossing between Capital Circle and Adelaide Avenue.

The final documents have proposed several posted speed limit changes for roads in the Commonwealth Avenue, Parliament House and Inner South precincts.

“[The changes create] a more predictable environment through the transition from Capital Circle to Adelaide Avenue, and promote awareness and visibility through the curve,” the documents stated.

No posted speed limit changes were suggested for the Yarra Glen or Woden precincts.

table showing speed limit changes

Changes to posted speed limits for light rail stage 2B. Photo: ACT Government.

Other additions include more kiss-and-ride spaces at the Hopetoun Circuit, Kent Street and Carruthers Street stops; lighting installation along the active travel path on the eastern side of Yarralumla Creek; improvements to accessibility and connectivity at the Kent Street and Carruthers Street stops; consideration of a Customer Service Officer facility at the Phillip Oval stop; more construction compound sites; and an extra track cross-over on Commonwealth Avenue after the Albert Hall stop.

READ ALSO Snowy Hydro executives take home $750,000 in bonuses

As previously announced, a major design change has been made for the track along State Circle, between Commonwealth Avenue and Adelaide Avenue, from a ‘median running’ arrangement to an ‘inner running’ arrangement between Sydney Avenue and Adelaide Avenue.

“This moves the proposed light rail infrastructure, including the Melbourne Avenue stop, from the median of State Circle to the inner verge on the Capital Hill side,” the documents stated.

This would mean State Circle would no longer need to be widened past Sydney Avenue, motorists would still be able to turn right to access the Presbyterian Church of St Andrew, and the existing street parking and loading zone on State Circle between Hobart Avenue and west of Melbourne Avenue would remain.

The left slip lanes would be removed at the Sydney Avenue intersection.

“This will help to retain existing parking arrangements and reduce disruption to nearby residents, businesses and the road network.”

map showing difference between median running and inner running track arrangement for light rail stage 2B

The final EIS documents include a switch to an inner track arrangement on State Circle, south of Sydney Avenue. Photo: ACT Government.

The covered section between Commonwealth Avenue and State Circle remains in the final documents.

The 125-metre-long section under the southbound carriageway of Commonwealth Avenue would emerge on State Circle without disrupting southbound traffic on Commonwealth Avenue.

How this would be achieved depends on further investigation and consultation.

“Any alternative solution would balance factors including traffic and road network performance, urban design and visual impacts, and heritage considerations,” the documents stated.

Both the Commonwealth and ACT Governments must now consider the EIS and decide whether the project can proceed and, if so, under what conditions.

This decision is expected by the end of the year.

If the environmental approval process is cleared, detailed design work will then need to begin to support planning approvals, including a Works Approval from the National Capital Authority and a development approval from the Territory Planning Authority (TPA).

Parts of the project within the Parliamentary Zone will also require approval from both Houses of Parliament.

“Once planning approvals are complete, Infrastructure Canberra will develop a detailed business case to inform government investment decisions,” the documents stated.

“This ensures funding and delivery decisions are based on a clearly defined scope and detailed investigations. There will be more opportunities to have your say on the project as it progresses through these next steps.”

Original Article published by Claire Fenwicke on Region Canberra.

Subscribe to PS News

Sign up now for all your free Public Sector and Defence news, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Be among the first to get all the Public Sector and Defence news and views that matter.

Subscribe now and receive the latest news, delivered free to your inbox.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.