Yass Valley Council has outlined its plan to block data centres in parts of the region. Photo: Canberra Data Centres.
A regional NSW council is moving to limit where data centres can go, in hopes of blocking “cowboy operators”.
The move was sparked by a Yass Valley Council mayoral minute from earlier this year, which hit out against the possibility of a local data centre due to water, land availability and amenity concerns.
Part of it called for the council to rule out data centres as an appropriate use of rural land in the area.
A staff member told councillors the proposed change was another tool for the council to use when assessing a future proposal.
Under the proposal, ‘high technology’ would be ruled out from land zoned as RU1, RU2 and RU4.
“What this does is send a message that these areas, given their productive agricultural nature, their lifestyle impacts, the proximity of other agricultural activities … aren’t really appropriate for what’s really a defined light industrial usage.”
But he acknowledged that, if a project was declared as a state significant development, there wasn’t anything the council could do.
In that scenario, proposals are decided by the Minister for Planning or the Independent Planning Commission.
Mayor Jasmin Jones said she believed data centre interest was being driven by work on energy infrastructure in the wider region.
“It’s very clear that the power-hungry nature of data centres is essentially why we have a target on our back right now, because of the capacity of HumeLink to carry that energy through Yass Valley,” she told the meeting.
“That, essentially, is it – the nexus of our location and our proximity to power.”
In its 2026 Transmission Annual Planning Report, Transgrid outlined its hopes for network capacity, including for data centres.
Among its hopes is for Yass and Wagga Wagga to host between 1 and 2 GW of data centre-related infrastructure.
Marulan (near Goulburn) and Canberra are also flagged as host sites for up to 1 GW.
During the meeting, Mayor Jones updated fellow councillors on plans to meet with stakeholders, including the Transgrid CEO, as noted in the mayoral minute.
She said there had been a “passive presentation” about the energy company’s approach to data centres in NSW, while a separate meeting was planned to probe why the area was flagged in the report.

Yass, Marulan and Wagga Wagga are suggested as host sites in an annual Transgrid report. Image: Transgrid.
Councillor Adrian Cameron said that while he would support the overall motion, there were “some deficiencies” in its wording.
He asked why data centres weren’t specified in the proposal (with ‘high technologies’ being used instead), saying this risked locking YVC out of that industry.
“[In the event] we move away from tourism … high value tech industries might be quite valuable for the valley.”
In response, a staff member said that within the planning process, they weren’t able to single out data centres.
“What we have to do is exclude the overarching definition … which is the ‘high technology industries’ … We have to either include or exclude the entire definition.”
Mayor Jones called for the council to treat potential data centres in a similar way to renewable energy projects.
She said that doing otherwise risked having “cowboy operators” coming into the area and pushing ahead with projects, “regardless of the existing and well-established agricultural and destination tourism experiences”.
“We have an opportunity … to actually set some boundaries, to lasso and corral this into an area where it is then on the proponent to prove that it’s in the best interests of Yass Valley.”
The vote means the proposal will move to a Gateway Determination. If it passes that stage, it will then be put out for public exhibition.
Original Article published by Claire Sams on About Regional.